Facilities (81)
View the map · Download the JSON file
| Facility | State | Place | Operator | Status | Kind | Checked | MW | Capacity note |
|---|---|---|---|---|---|---|---|---|
| Aligned PHX05 | Arizona | Phoenix | Aligned Data Centers | Planned (as of a 2022 announcement) | proposal | dossier | — | Not stated |
| Aligned PHX13 Glendale | Arizona | Glendale | Aligned Data Centers | Under construction (groundbreaking Apr. 15, 2025) | facility | dossier | 72 | 72 MW (city release); 100-acre campus, four planned facilities |
| Aligned Union Hills | Arizona | Phoenix | Aligned Data Centers | Listed on operator location page; status not stated | proposal | dossier | — | Not stated |
| Amazon Mesa (Pecos and Elliot roads) | Arizona | Mesa | Amazon (named in listing data) | Pecos listed as under construction, planned 2026 (listing; not confirmed) | facility | dossier | — | Two 227,000 sq ft buildings per listing |
| Compass El Mirage campus | Arizona | El Mirage | Compass Datacenters | Site plan approved by El Mirage (reported); construction status conflicts | proposal | dossier | — | Three buildings, 208,000 sq ft each (plans as reported) |
| Compass Goodyear campus | Arizona | Goodyear (Bullard Ave. and Yuma Rd.) | Compass Datacenters | 2019 city release; status not confirmed | proposal | dossier | 350 | 350 MW at build-out (2019 city release); 212 MW on market page |
| CyrusOne Chandler PHX1–PHX8 | Arizona | Chandler | CyrusOne | Eight facilities per operator | facility | dossier | — | Operator states zero-water cooling (company claim) |
| CyrusOne Mesa Crismon | Arizona | Mesa | CyrusOne | Special use permit approved 4-3; rezoning recommended 6-0 (July 2024) | proposal | dossier | — | About 67 acres |
| Digital Realty PHX15 | Arizona | Chandler (2121 S. Price Road) | Digital Realty | Operator-listed facility | facility | dossier | — | 508,000 sq ft, two stories (operator page) |
| EdgeConneX PHX01 | Arizona | Tempe | EdgeConneX | Existing facility per 2024 data sheet; current status not confirmed | facility | dossier | 6.5 | 4.5 MW N+1, scalable to 6.5 MW (data sheet) |
| EdgeConneX PHX11 | Arizona | Mesa (8604 E. Elliot Road) | EdgeConneX | Site applications reported Sept. 2023; no approval found | proposal | dossier | 115.2 | 115.2 MW planned (data sheet); other figures conflict |
| Edged Energy Mesa PHX01 | Arizona | Mesa | Edged Energy | Listed as launched April 2026; no permit record retrieved | facility | dossier | 36 | 36 MW (listing); building area conflicts |
| Flexential Phoenix Deer Valley | Arizona | Phoenix (Deer Valley) | Flexential | Operator sheet, Nov. 2025 | facility | dossier | 5.02 | 5.02 MW critical-load UPS (operator sheet) |
| Google Mesa | Arizona | Mesa (Elliot and Ellsworth roads) | Listed by operator; no status on page; earlier acreage claim withdrawn | proposal | dossier | — | Acreage unverified; see page correction | |
| H5 Data Centers Chandler | Arizona | Chandler (2600 W. Germann Road) | H5 Data Centers | Phase 3 (30,000 sq ft) announced June 29, 2023 (H5 release) | facility | checked | 26 | Up to 26 MW IT load (H5 release, June 2023); other reports say 20 and 30 MW |
| Iron Mountain AZP-1 | Arizona | Phoenix (east of downtown) | Iron Mountain | Operating (operator page) | facility | dossier | 41 | 41 MW power capacity; Tier III (operator) |
| Iron Mountain AZP-2 | Arizona | Phoenix (east of downtown) | Iron Mountain | Operating (operator page) | facility | dossier | 48 | Up to 48 MW critical IT (operator) |
| Iron Mountain AZP-3 | Arizona | Phoenix | Iron Mountain | Operational (operator overview) | facility | dossier | — | Capacity not documented in retrieved text |
| Iron Mountain AZS-1 | Arizona | Scottsdale (northeast corridor) | Iron Mountain | Operating (operator page) | facility | dossier | 9.6 | 5.8 MW, expandable to 9.6 MW (operator) |
| Judd Ventures San Tan Valley | Arizona | San Tan Valley (Pinal County) | Judd Ventures LLC (applicant) | Major comprehensive plan amendment, case PZ-PA-012-24 | proposal | dossier | — | About 96 acres |
| Legacy Business Park data center | Arizona | Mesa | Merit Partners (applicant) | Planning board approval with conditions, 5-0; council use permit pending | proposal | dossier | — | About 43 acres |
| Luckett Road, Marana | Arizona | Marana | Applicant per town filings | Town Council rezoning approved Jan. 6, 2026; referendum petitions rejected; litigation | proposal | dossier | — | About 600 acres in two parcels |
| Metro North Corporate Park | Arizona | Phoenix | Dimension Financial & Realty Investments (owner) | PUD amendment dated Oct. 27, 2025; adoption not confirmed | proposal | dossier | — | 100,000 sq ft raised-floor cap (PUD text) |
| Microsoft El Mirage campus | Arizona | El Mirage and Goodyear | Microsoft | Announced July 30, 2019; construction not confirmed | proposal | dossier | — | 150 MW solar plant announced (Sun Streams 2) |
| Microsoft Goodyear campus | Arizona | Goodyear | Microsoft | Announced July 30, 2019; construction not confirmed | proposal | dossier | — | 150 MW solar plant announced (Sun Streams 2) |
| NTT Mesa PH10 | Arizona | Mesa | NTT | Planning board recommended approval 4-0, May 13, 2026; council pending | proposal | dossier | — | About 170 acres; 2.26M sq ft proposed (staff report) |
| Novva Mesa campus | Arizona | Mesa (Loop 202 at Ellsworth and Warner roads) | Novva | Phase one scheduled late 2026 in a 2024-era report; not confirmed | proposal | dossier | 96 | First phase 96 MW (report) |
| Pacific Proving Technology Campus | Arizona | Mesa | Pacific Proving, LLC | City Council approved unanimously Aug. 26, 2024 (press reports) | facility | dossier | — | About 177 acres |
| Prime PHX01–02 Avondale | Arizona | Avondale | Prime Data Centers | Under construction: groundbreaking May 21, 2026 (company release) | facility | dossier | 240 | 240 MW IT across five buildings (company release) |
| Project Baccara Eagle | Arizona | Maricopa County | Takanock (per Commission statement) | Arizona Corporation Commission approved 5-0, Feb. 4, 2026; county approval May 6, 2026 (KOLD) | proposal | dossier | 700 | 700 MW gas plant (Baccara Power); not data-center load |
| Project Blue, Tucson | Arizona | Tucson (unincorporated Pima County) | Developer per Pima County filings | Construction reported underway since April 2026; city rules adopted Aug. 5, 2026 | facility | dossier | — | Large-scale data-center rules adopted (6-1) |
| Project Midway, Pinal County | Arizona | Pinal County | Applicant per Pinal County filings | Comprehensive plan amendment reported approved Nov. 2025 (secondary report) | proposal | dossier | — | About 215 acres |
| QTS Phoenix II | Arizona | Phoenix (40th St. and McDowell Road) | QTS Phoenix II, LLC | Council item Dec. 13, 2023 (Ordinance S-50411) | proposal | dossier | — | About 97.85 acres |
| Stream Goodyear campus | Arizona | Goodyear (2950 S. Litchfield Road) | Stream Data Centers | Seven buildings planned on 157+ acres; first two serving tenants (operator) | facility | checked | 280 | 280 MW critical load at full build (operator); substation 480 MW (operator) vs 350 MW (2019 city release) |
| Vantage AZ1 Goodyear | Arizona | Goodyear | Vantage Data Centers | Operator release (2021); later reports describe five planned buildings | facility | dossier | 160 | 160 MW IT across three facilities (2021 operator release) |
| Vantage Goodyear Phase II | Arizona | Goodyear | Vantage Data Centers | Topped out July 2023; operating date scheduled spring 2024 | facility | checked | 176 | 176 MW IT across three facilities (operator, July 2023); 160 MW in a 2021 release |
| Vermaland La Osa | Arizona | Eloy (Pinal County) | Vermaland LLC | Campus cut to 11 buildings after May 2026 opposition (ABC15, July 20, 2026); planning and zoning items on July 16 agenda | proposal | checked | — | 3,300 acres; 11 buildings (was 59) |
| Canoochee River RV Resort data center | Georgia | Metter (Candler County) | Canoochee River RV Resort, LLC | DRI application filed Oct. 2026; county rezoning to PUD pending; completion targeted 2033 | proposal | checked | — | Five buildings up to 250,000 sq ft each on 470 acres; two substations (Baxtel) |
| Forsyth Technology Campus | Georgia | Forsyth (Monroe County) | Developer named in state filings (H&H Timberlands owners) | Rezoning approved by Forsyth city council, Feb. 2, 2026 (GPB); 1,600-acre timberland site | facility | checked | — | State filings: $224M a year projected in city tax revenue; city water permit 4 MGD (about half projected need) |
| Project Arrowhead, Irwin County | Georgia | Mystic area (Irwin County) | Premier Data Center Development LLC | DRI application filed Apr. 2026; Georgia Power energy study underway; first phase targeted 2030 | proposal | checked | 1,250 | Five buildings, 4.22M sq ft on about 1,000 acres; 1.25 GW; up to $6B (Baxtel) |
| Project Azalea | Georgia | Thomson (McDuffie County) | Project Turbo LLC (linked developer) | Approved 4-1 by county commission, Mar. 2026; utility study says sufficient supply is not yet available (Baxtel) | proposal | checked | 400 | Six buildings on 200 acres; 400 MW planned supply from Jefferson Energy; $1B (Baxtel) |
| Project Camellia (OpenAI) | Georgia | Rincon (Effingham County) | OpenAI (developer per The Current; Octans GA LLC on DRI form) | Announced July 22, 2026; DRI form submitted; four buildings on about 101 acres; launch projected 2028 | proposal | checked | 3,200 | 3.2 GW of Georgia Power supply, phased 2028–2032 (The Current); not an IT-load figure |
| Project Sail | Georgia | Newnan (Coweta County) | Prologis | Rezoning approved 3-2, Apr. 7, 2026 | facility | checked | 900 | 900 MW (DCD via Pulse); not in other sources |
| Wallace Jackson Data Center Campus | Georgia | Griffin (Spalding County) | Wallace Jackson LLC | Proposed Jan. 2026 (AJC); county zoning approved Jan. 22, 2026 per IDCnova (secondary) | facility | checked | — | AJC: $3.7B, 10 buildings, nearly 5M sq ft, about 190 acres; approved figure $3.9B (secondary) |
| Aligned Coal City campus | Illinois | Coal City (Grundy County) | Aligned Data Centers | PUD petition under village review; no Board vote found | proposal | checked | — | Not confirmed in checked sources |
| Digital Realty Kokomo campus | Indiana | Kokomo (Howard County) | Digital Realty | Proposed; site plan targets completion in 2033 (Baxtel, Oct. 16, 2026) | proposal | checked | 1,000 | 1 GW IT capacity across three million sq ft on 476 acres (Baxtel, one source) |
| Google Franklin Township proposal | Indiana | Indianapolis (Franklin Township) | Rezoning petition withdrawn Sept. 22, 2025 | proposal | checked | — | 468 acres rezoning; no MW stated | |
| Google Monrovia campus | Indiana | Monrovia (Morgan County) | Google (per state filings and coverage) | Utility plan approved Oct. 7, 2026; construction timeline not disclosed | facility | checked | 390 | 390 MW (GCN) |
| Meta Lebanon campus | Indiana | Lebanon (Boone County) | Meta Platforms | Groundbreaking Feb. 11, 2026; first phase late 2027 or early 2028 | facility | checked | 1,000 | 1 GW (company announcement) |
| Prologis Shelbyville campus | Indiana | Shelbyville (Shelby County) | Prologis (no end user identified) | Annexation and rezoning requested, Jan. 2026; Plan Commission and Council review; petition against with 2,100+ signatures | proposal | checked | — | Up to 13 buildings on about 576 acres after annexation (Construction Owners, Jan. 7, 2026) |
| Sabey Decatur campus | Indiana | Indianapolis (Decatur Township) | Sabey Data Centers | Commission approval Mar. 18, 2026; tax incentives pending | facility | checked | 250 | 250 MW over five years (Mirror Indy) |
| Project Bluestem | Kansas | Tonganoxie (Leavenworth County) | Cloverleaf Infrastructure | Under county review; no permit application filed as of Aug. 2026; moratorium expired | proposal | checked | 1,200 | 1.2 GW with on-site gas plant (KSHB) |
| Amazon data center campus | Missouri | Montgomery County, eastern Missouri | Amazon | Announced June 15, 2026; groundbreaking and opening dates not released | proposal | checked | — | $10B; about 400 direct jobs; Amazon pays 100% of electric service costs (Missourinet, June 15, 2026) |
| Google Montgomery County campus | Missouri | New Florence (Montgomery County) | Announced May 21, 2026 | proposal | checked | — | $15B statewide; Google's 1 GW+ is generation contracted in Missouri, not campus load (release) | |
| Google Project Mica | Missouri | Kansas City (Northland) | Google confirmed Feb. 12, 2026; Port KC bonds up to $10B authorized | facility | checked | 500 | Up to 500 MW (Axios); project materials cite nearly 700 MW supply | |
| Metrobloks Liberty campus | Missouri | Liberty (Clay County) | Metrobloks | Announced Mar. 24, 2026; construction schedule not stated | proposal | checked | — | $1.4B; 568,800 sq ft; power capacity not stated |
| Nebius Independence campus | Missouri | Independence (Jackson County) | Nebius | Broke ground May 2026; first phase expected mid-2027 (chairman) | facility | checked | 800 | 800 MW (Axios, Sept. 25, 2026); 1.2 GW in an earlier source |
| Big Woods Technology Park, Jefferson Davis County | Mississippi | Jefferson Davis County | Eagle Rock Partners | Planned; on-site gas generation needs Mississippi DEQ approval before operation (Planetizen, Oct. 4, 2026) | proposal | checked | — | $6B, roughly 2M sq ft; 1,000 temporary and 200 permanent jobs (Planetizen) |
| Energy Storage Solutions data center campus | North Carolina | Rocky Mount area (Edgecombe County) | Energy Storage Solutions | Zoning amended Nov. 2025; land sale pending county approval as of Nov. 2025 (WFAE) | proposal | checked | 900 | $19B; 900 MW; 300-acre site per WFAE (a Baxtel summary gives 155 acres, not checked) |
| Person County Mega Park data center | North Carolina | North of Roxboro (Person County) | Microsoft | Land bought Oct. 2024; permitting reportedly begins 2026 (Bisnow, Feb. 2026) | proposal | checked | — | About 1,350 acres (Bisnow); Baxtel summary says 1,385 (not checked); capacity not disclosed |
| WhiteFiber AI data center campus | North Carolina | Yadkin County | WhiteFiber | Acquisition agreed ($60M, close expected fall 2026); two-year county moratorium approved | proposal | checked | 200 | 60 MW initial; up to about 200 MW potential (WUNC, Aug. 19, 2026) |
| Bristolville 25 campus, Lordstown | Ohio | Lordstown (Trumbull County) | Bristolville 25 Developer LLC (Dublin, Ohio) | Ohio Supreme Court ruled Oct. 20, 2026 that the village may pause review (LDS summary of the ruling) | proposal | checked | — | $3.6B, four three-story buildings, about 130 acres (Business Journal Daily via LDS) |
| Crane Data Centers, Pierce Township | Ohio | Pierce Township (Clermont County) | Crane Data Centers (San Francisco) | Proposed to Pierce Township zoning commission, Sept. 2026; township moratorium in place; trustees still to review | proposal | checked | 300 | 300 MW; three buildings on 300 acres beside the closed Beckjord plant (WVXU) |
| Google Lima campus | Ohio | American Township near Lima (Allen County) | Google (identified by local leaders, Mar. 2026) | Under state air-permit review; draft permit covers more than 100 diesel generators (WLZZ, one local source) | proposal | checked | — | $500M on more than 200 acres; about $50M in roadwork (WLZZ) |
| Lakeland Equity campus, Cleveland | Ohio | Cleveland (Slavic Village) | Lakeland Equity Group (end user undisclosed) | Permit denied by the city, May 14, 2026 (Baxtel) | proposal | checked | 150 | 150 MW, three buildings, 300,000 sq ft on 35 acres; $1.6B (Baxtel) |
| Beltline Energy data center (Oklahoma City) | Oklahoma | Oklahoma City, near I-40 and Frisco Road | Beltline Energy | Rezoning approved with conditions, Oct. 27, 2026; further agreements needed before construction | proposal | checked | — | Conditions cover water, electricity and noise; numeric limits not given (News 9) |
| Google Muskogee County campuses | Oklahoma | Summit and Council Hill (Muskogee County) | Announced Nov. 20, 2025; OG&E contracts; campus size not stated | proposal | checked | — | 600 MW of new solar PPAs (not campus load) | |
| Lambda Mayes County campus | Oklahoma | Chouteau (Mayes County) | Lambda | Announced Sept. 27, 2026; timeline not released | proposal | checked | — | Not stated; company says it will pay all energy costs |
| Project Clydesdale | Oklahoma | Unincorporated Tulsa County, near Owasso | Google (operator); Beale Infrastructure (developer) | Under construction per Google and Beale release, Aug. 19, 2026 | facility | checked | — | 506 acres; powered by PSO with a new onsite substation; capacity not stated |
| Project Thunderbird (Enid Data Center and Power Campus) | Oklahoma | Enid (Garfield County), four sites | Plainsman Holdings LLC | Proposed; not approved; rezoning filed for two sites (News 9, Sept. 2026) | proposal | checked | 2,750 | 2.75 GW IT load and 3.3 GW on-site gas generation (developer; News 9, Sept. 8, 2026) |
| Aligned Project Phoenix | Pennsylvania | Shippingport (Beaver County) | Aligned Data Centers | Groundbreaking reported Sept. 17, 2026 (DCD); approval date conflicts | facility | checked | 2,000 | 2 GW (company, DCD) |
| Project River energy and data center campus | Tennessee | West of Cleveland, Bradley County (west of I-75) | Wright Brothers Construction | Rezoning and annexation into Cleveland submitted (Aug. 2026); offtaker not chosen | proposal | checked | 1,500 | $11.3B; 850 acres; 1,500 MW on-site generation; 360 MW TVA backup/peak requested (News 9, Aug. 26, 2026) |
| Crusoe Stargate campus | Texas | Abilene (Taylor County) | Crusoe (tenants Oracle and OpenAI; Microsoft buildings planned) | Two buildings operational (Sept. 2025 report); more under construction; disputes reported Mar. 2026 | facility | checked | 2,100 | 1.2 GW OpenAI/Oracle campus; 2.1 GW with Microsoft (AP) |
| Project Caprock | Texas | Abernathy (Hale County) | Aligned Data Centers | Construction begun (company); first building targeted Q1 2027 | facility | checked | 540 | 540 MW planned (company) |
| Taylor Technology Campus (Project Mustang) | Texas | Taylor (Williamson County) | Big Watt Digital and PowerHouse Data Centers | Council approved unanimously, Oct. 8, 2026 (KUT) | facility | checked | — | 664 acres; no capacity stated in KUT (Oct. 9, 2026); $28.2M community investment estimate (developers) |
| Berry Hill campus (STACK, Project Crossroads) | Virginia | Berry Hill, Pittsylvania County (Danville area) | STACK Infrastructure (end user unknown) | Joint state and federal application filed Oct. 2026; permit decision expected by March 2027 | proposal | checked | 3,000 | 21 buildings over 15 years; up to 3,000 MW ceiling (not guaranteed); up to 7 MGD water; $100B (WDBJ, Oct. 26, 2026) |
| CloudHQ LC Ashburn | Virginia | Ashburn (Loudoun County) | CloudHQ | Operator page: ready for service within 20 months | facility | dossier | 1,256 | 1,256 MW total; 756 MW critical IT (operator) |
| SF DC1 Vienna (Tysons) | Virginia | Tysons (Fairfax County) | SF DC1 LLC | Applicant asked to defer special exception indefinitely (Oct. 2026) | proposal | dossier | — | About 316,228 sq ft; 14.4 acres |
| Microsoft Caledonia site | Wisconsin | Caledonia (Racine County) | Microsoft | Withdrawn Oct. 8, 2025 after community opposition; company seeking another site | proposal | checked | — | 244 acres; no MW stated |
| Microsoft Mount Pleasant expansion (15 proposed data centers) | Wisconsin | Mount Pleasant (Racine County), former Foxconn site | Microsoft | Planning commission recommended conditional approval, Jan. 2026 | proposal | checked | — | 15 data centers in two campuses, over $13B (WPR, Jan. 20, 2026); no energy estimate published |
| Vantage Lighthouse campus | Wisconsin | Port Washington (Ozaukee County) | Vantage Data Centers | Being constructed (DNR); air permits issued June 12, 2026; phases through 2034 | facility | checked | 1,300 | 1.3 GW (city and WPR figure) |