 "updated": "2026-11-08",
 "count": 81,
 "records": [
  {
   "slug": "project-caprock-abernathy-tx",
   "name": "Project Caprock",
   "operator": "Aligned Data Centers",
   "state": "TX",
   "place": "Abernathy (Hale County)",
   "lat": 33.83,
   "lon": -101.84,
   "precision": "city",
   "kind": "facility",
   "status": "Construction begun (company); first building targeted Q1 2027",
   "mw": 540,
   "mw_note": "540 MW planned (company)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "aligned-project-phoenix-shippingport-pa",
   "name": "Aligned Project Phoenix",
   "operator": "Aligned Data Centers",
   "state": "PA",
   "place": "Shippingport (Beaver County)",
   "lat": 40.56,
   "lon": -80.43,
   "precision": "city",
   "kind": "facility",
   "status": "Groundbreaking reported Sept. 17, 2026 (DCD); approval date conflicts",
   "mw": 2000,
   "mw_note": "2 GW (company, DCD)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "aligned-coal-city-il",
   "name": "Aligned Coal City campus",
   "operator": "Aligned Data Centers",
   "state": "IL",
   "place": "Coal City (Grundy County)",
   "lat": 41.28,
   "lon": -88.29,
   "precision": "city",
   "kind": "proposal",
   "status": "PUD petition under village review; no Board vote found",
   "mw": null,
   "mw_note": "Not confirmed in checked sources",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "crusoe-stargate-abilene-tx",
   "name": "Crusoe Stargate campus",
   "operator": "Crusoe (tenants Oracle and OpenAI; Microsoft buildings planned)",
   "state": "TX",
   "place": "Abilene (Taylor County)",
   "lat": 32.45,
   "lon": -99.73,
   "precision": "city",
   "kind": "facility",
   "status": "Two buildings operational (Sept. 2025 report); more under construction; disputes reported Mar. 2026",
   "mw": 2100,
   "mw_note": "1.2 GW OpenAI/Oracle campus; 2.1 GW with Microsoft (AP)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "prologis-project-sail-coweta-ga",
   "name": "Project Sail",
   "operator": "Prologis",
   "state": "GA",
   "place": "Newnan (Coweta County)",
   "lat": 33.38,
   "lon": -84.8,
   "precision": "city",
   "kind": "facility",
   "status": "Rezoning approved 3-2, Apr. 7, 2026",
   "mw": 900,
   "mw_note": "900 MW (DCD via Pulse); not in other sources",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "meta-lebanon-in",
   "name": "Meta Lebanon campus",
   "operator": "Meta Platforms",
   "state": "IN",
   "place": "Lebanon (Boone County)",
   "lat": 40.05,
   "lon": -86.47,
   "precision": "city",
   "kind": "facility",
   "status": "Groundbreaking Feb. 11, 2026; first phase late 2027 or early 2028",
   "mw": 1000,
   "mw_note": "1 GW (company announcement)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "google-monrovia-in",
   "name": "Google Monrovia campus",
   "operator": "Google (per state filings and coverage)",
   "state": "IN",
   "place": "Monrovia (Morgan County)",
   "lat": 39.67,
   "lon": -86.42,
   "precision": "city",
   "kind": "facility",
   "status": "Utility plan approved Oct. 7, 2026; construction timeline not disclosed",
   "mw": 390,
   "mw_note": "390 MW (GCN)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "sabey-decatur-indianapolis-in",
   "name": "Sabey Decatur campus",
   "operator": "Sabey Data Centers",
   "state": "IN",
   "place": "Indianapolis (Decatur Township)",
   "lat": 39.7,
   "lon": -86.25,
   "precision": "city",
   "kind": "facility",
   "status": "Commission approval Mar. 18, 2026; tax incentives pending",
   "mw": 250,
   "mw_note": "250 MW over five years (Mirror Indy)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "aligned-phx13-glendale",
   "name": "Aligned PHX13 Glendale",
   "operator": "Aligned Data Centers",
   "state": "AZ",
   "place": "Glendale",
   "lat": 33.54,
   "lon": -112.19,
   "precision": "city",
   "kind": "facility",
   "status": "Under construction (groundbreaking Apr. 15, 2025)",
   "mw": 72,
   "mw_note": "72 MW (city release); 100-acre campus, four planned facilities",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "aligned-phx05",
   "name": "Aligned PHX05",
   "operator": "Aligned Data Centers",
   "state": "AZ",
   "place": "Phoenix",
   "lat": 33.45,
   "lon": -112.07,
   "precision": "city",
   "kind": "proposal",
   "status": "Planned (as of a 2022 announcement)",
   "mw": null,
   "mw_note": "Not stated",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "aligned-phoenix-union-hills",
   "name": "Aligned Union Hills",
   "operator": "Aligned Data Centers",
   "state": "AZ",
   "place": "Phoenix",
   "lat": 33.61,
   "lon": -112.14,
   "precision": "city",
   "kind": "proposal",
   "status": "Listed on operator location page; status not stated",
   "mw": null,
   "mw_note": "Not stated",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "amazon-mesa-pecos-elliot",
   "name": "Amazon Mesa (Pecos and Elliot roads)",
   "operator": "Amazon (named in listing data)",
   "state": "AZ",
   "place": "Mesa",
   "lat": 33.37,
   "lon": -111.75,
   "precision": "city",
   "kind": "facility",
   "status": "Pecos listed as under construction, planned 2026 (listing; not confirmed)",
   "mw": null,
   "mw_note": "Two 227,000 sq ft buildings per listing",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "cloudhq-lc-ashburn",
   "name": "CloudHQ LC Ashburn",
   "operator": "CloudHQ",
   "state": "VA",
   "place": "Ashburn (Loudoun County)",
   "lat": 39.01,
   "lon": -77.46,
   "precision": "city",
   "kind": "facility",
   "status": "Operator page: ready for service within 20 months",
   "mw": 1256,
   "mw_note": "1,256 MW total; 756 MW critical IT (operator)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "compass-el-mirage-campus",
   "name": "Compass El Mirage campus",
   "operator": "Compass Datacenters",
   "state": "AZ",
   "place": "El Mirage",
   "lat": 33.61,
   "lon": -112.32,
   "precision": "city",
   "kind": "proposal",
   "status": "Site plan approved by El Mirage (reported); construction status conflicts",
   "mw": null,
   "mw_note": "Three buildings, 208,000 sq ft each (plans as reported)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "compass-goodyear-campus",
   "name": "Compass Goodyear campus",
   "operator": "Compass Datacenters",
   "state": "AZ",
   "place": "Goodyear (Bullard Ave. and Yuma Rd.)",
   "lat": 33.44,
   "lon": -112.36,
   "precision": "city",
   "kind": "proposal",
   "status": "2019 city release; status not confirmed",
   "mw": 350,
   "mw_note": "350 MW at build-out (2019 city release); 212 MW on market page",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "cyrusone-chandler-phx1-phx8",
   "name": "CyrusOne Chandler PHX1–PHX8",
   "operator": "CyrusOne",
   "state": "AZ",
   "place": "Chandler",
   "lat": 33.31,
   "lon": -111.84,
   "precision": "city",
   "kind": "facility",
   "status": "Eight facilities per operator",
   "mw": null,
   "mw_note": "Operator states zero-water cooling (company claim)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "cyrusone-mesa-crismon",
   "name": "CyrusOne Mesa Crismon",
   "operator": "CyrusOne",
   "state": "AZ",
   "place": "Mesa",
   "lat": 33.42,
   "lon": -111.83,
   "precision": "city",
   "kind": "proposal",
   "status": "Special use permit approved 4-3; rezoning recommended 6-0 (July 2024)",
   "mw": null,
   "mw_note": "About 67 acres",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "digital-realty-phx15",
   "name": "Digital Realty PHX15",
   "operator": "Digital Realty",
   "state": "AZ",
   "place": "Chandler (2121 S. Price Road)",
   "lat": 33.31,
   "lon": -111.89,
   "precision": "city",
   "kind": "facility",
   "status": "Operator-listed facility",
   "mw": null,
   "mw_note": "508,000 sq ft, two stories (operator page)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "edgeconnex-phx01-tempe",
   "name": "EdgeConneX PHX01",
   "operator": "EdgeConneX",
   "state": "AZ",
   "place": "Tempe",
   "lat": 33.43,
   "lon": -111.94,
   "precision": "city",
   "kind": "facility",
   "status": "Existing facility per 2024 data sheet; current status not confirmed",
   "mw": 6.5,
   "mw_note": "4.5 MW N+1, scalable to 6.5 MW (data sheet)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "edgeconnex-phx11-mesa",
   "name": "EdgeConneX PHX11",
   "operator": "EdgeConneX",
   "state": "AZ",
   "place": "Mesa (8604 E. Elliot Road)",
   "lat": 33.31,
   "lon": -111.64,
   "precision": "city",
   "kind": "proposal",
   "status": "Site applications reported Sept. 2023; no approval found",
   "mw": 115.2,
   "mw_note": "115.2 MW planned (data sheet); other figures conflict",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "edged-energy-mesa-phx01",
   "name": "Edged Energy Mesa PHX01",
   "operator": "Edged Energy",
   "state": "AZ",
   "place": "Mesa",
   "lat": 33.41,
   "lon": -111.8,
   "precision": "city",
   "kind": "facility",
   "status": "Listed as launched April 2026; no permit record retrieved",
   "mw": 36,
   "mw_note": "36 MW (listing); building area conflicts",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "flexential-phoenix-deer-valley",
   "name": "Flexential Phoenix Deer Valley",
   "operator": "Flexential",
   "state": "AZ",
   "place": "Phoenix (Deer Valley)",
   "lat": 33.68,
   "lon": -112.08,
   "precision": "city",
   "kind": "facility",
   "status": "Operator sheet, Nov. 2025",
   "mw": 5.02,
   "mw_note": "5.02 MW critical-load UPS (operator sheet)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "google-mesa",
   "name": "Google Mesa",
   "operator": "Google",
   "state": "AZ",
   "place": "Mesa (Elliot and Ellsworth roads)",
   "lat": 33.36,
   "lon": -111.66,
   "precision": "city",
   "kind": "proposal",
   "status": "Listed by operator; no status on page; earlier acreage claim withdrawn",
   "mw": null,
   "mw_note": "Acreage unverified; see page correction",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "h5-phoenix-chandler",
   "name": "H5 Data Centers Chandler",
   "operator": "H5 Data Centers",
   "state": "AZ",
   "place": "Chandler (2600 W. Germann Road)",
   "lat": 33.27,
   "lon": -111.9,
   "precision": "city",
   "kind": "facility",
   "status": "Phase 3 (30,000 sq ft) announced June 29, 2023 (H5 release)",
   "mw": 26,
   "mw_note": "Up to 26 MW IT load (H5 release, June 2023); other reports say 20 and 30 MW",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "iron-mountain-azp1",
   "name": "Iron Mountain AZP-1",
   "operator": "Iron Mountain",
   "state": "AZ",
   "place": "Phoenix (east of downtown)",
   "lat": 33.45,
   "lon": -112.02,
   "precision": "city",
   "kind": "facility",
   "status": "Operating (operator page)",
   "mw": 41,
   "mw_note": "41 MW power capacity; Tier III (operator)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "iron-mountain-azp2",
   "name": "Iron Mountain AZP-2",
   "operator": "Iron Mountain",
   "state": "AZ",
   "place": "Phoenix (east of downtown)",
   "lat": 33.45,
   "lon": -112.02,
   "precision": "city",
   "kind": "facility",
   "status": "Operating (operator page)",
   "mw": 48,
   "mw_note": "Up to 48 MW critical IT (operator)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "iron-mountain-azp3",
   "name": "Iron Mountain AZP-3",
   "operator": "Iron Mountain",
   "state": "AZ",
   "place": "Phoenix",
   "lat": 33.45,
   "lon": -112.07,
   "precision": "city",
   "kind": "facility",
   "status": "Operational (operator overview)",
   "mw": null,
   "mw_note": "Capacity not documented in retrieved text",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "iron-mountain-azs1",
   "name": "Iron Mountain AZS-1",
   "operator": "Iron Mountain",
   "state": "AZ",
   "place": "Scottsdale (northeast corridor)",
   "lat": 33.62,
   "lon": -111.9,
   "precision": "city",
   "kind": "facility",
   "status": "Operating (operator page)",
   "mw": 9.6,
   "mw_note": "5.8 MW, expandable to 9.6 MW (operator)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "judd-ventures-san-tan-valley",
   "name": "Judd Ventures San Tan Valley",
   "operator": "Judd Ventures LLC (applicant)",
   "state": "AZ",
   "place": "San Tan Valley (Pinal County)",
   "lat": 33.2,
   "lon": -111.54,
   "precision": "city",
   "kind": "proposal",
   "status": "Major comprehensive plan amendment, case PZ-PA-012-24",
   "mw": null,
   "mw_note": "About 96 acres",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "legacy-business-park-data-center",
   "name": "Legacy Business Park data center",
   "operator": "Merit Partners (applicant)",
   "state": "AZ",
   "place": "Mesa",
   "lat": 33.4,
   "lon": -111.72,
   "precision": "city",
   "kind": "proposal",
   "status": "Planning board approval with conditions, 5-0; council use permit pending",
   "mw": null,
   "mw_note": "About 43 acres",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "luckett-road-marana",
   "name": "Luckett Road, Marana",
   "operator": "Applicant per town filings",
   "state": "AZ",
   "place": "Marana",
   "lat": 32.44,
   "lon": -111.22,
   "precision": "city",
   "kind": "proposal",
   "status": "Town Council rezoning approved Jan. 6, 2026; referendum petitions rejected; litigation",
   "mw": null,
   "mw_note": "About 600 acres in two parcels",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "metro-north-corporate-park",
   "name": "Metro North Corporate Park",
   "operator": "Dimension Financial & Realty Investments (owner)",
   "state": "AZ",
   "place": "Phoenix",
   "lat": 33.52,
   "lon": -112.07,
   "precision": "city",
   "kind": "proposal",
   "status": "PUD amendment dated Oct. 27, 2025; adoption not confirmed",
   "mw": null,
   "mw_note": "100,000 sq ft raised-floor cap (PUD text)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "microsoft-el-mirage-campus",
   "name": "Microsoft El Mirage campus",
   "operator": "Microsoft",
   "state": "AZ",
   "place": "El Mirage and Goodyear",
   "lat": 33.52,
   "lon": -112.31,
   "precision": "city",
   "kind": "proposal",
   "status": "Announced July 30, 2019; construction not confirmed",
   "mw": null,
   "mw_note": "150 MW solar plant announced (Sun Streams 2)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "microsoft-goodyear-campus",
   "name": "Microsoft Goodyear campus",
   "operator": "Microsoft",
   "state": "AZ",
   "place": "Goodyear",
   "lat": 33.44,
   "lon": -112.36,
   "precision": "city",
   "kind": "proposal",
   "status": "Announced July 30, 2019; construction not confirmed",
   "mw": null,
   "mw_note": "150 MW solar plant announced (Sun Streams 2)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "novva-mesa-campus",
   "name": "Novva Mesa campus",
   "operator": "Novva",
   "state": "AZ",
   "place": "Mesa (Loop 202 at Ellsworth and Warner roads)",
   "lat": 33.36,
   "lon": -111.66,
   "precision": "city",
   "kind": "proposal",
   "status": "Phase one scheduled late 2026 in a 2024-era report; not confirmed",
   "mw": 96,
   "mw_note": "First phase 96 MW (report)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "ntt-mesa-ph10",
   "name": "NTT Mesa PH10",
   "operator": "NTT",
   "state": "AZ",
   "place": "Mesa",
   "lat": 33.41,
   "lon": -111.79,
   "precision": "city",
   "kind": "proposal",
   "status": "Planning board recommended approval 4-0, May 13, 2026; council pending",
   "mw": null,
   "mw_note": "About 170 acres; 2.26M sq ft proposed (staff report)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "pacific-proving-technology-campus",
   "name": "Pacific Proving Technology Campus",
   "operator": "Pacific Proving, LLC",
   "state": "AZ",
   "place": "Mesa",
   "lat": 33.4,
   "lon": -111.78,
   "precision": "city",
   "kind": "facility",
   "status": "City Council approved unanimously Aug. 26, 2024 (press reports)",
   "mw": null,
   "mw_note": "About 177 acres",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "prime-phx01-02-avondale",
   "name": "Prime PHX01–02 Avondale",
   "operator": "Prime Data Centers",
   "state": "AZ",
   "place": "Avondale",
   "lat": 33.44,
   "lon": -112.35,
   "precision": "city",
   "kind": "facility",
   "status": "Under construction: groundbreaking May 21, 2026 (company release)",
   "mw": 240,
   "mw_note": "240 MW IT across five buildings (company release)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "project-baccara-eagle",
   "name": "Project Baccara Eagle",
   "operator": "Takanock (per Commission statement)",
   "state": "AZ",
   "place": "Maricopa County",
   "lat": 33.45,
   "lon": -112.07,
   "precision": "county",
   "kind": "proposal",
   "status": "Arizona Corporation Commission approved 5-0, Feb. 4, 2026; county approval May 6, 2026 (KOLD)",
   "mw": 700,
   "mw_note": "700 MW gas plant (Baccara Power); not data-center load",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "project-blue-tucson",
   "name": "Project Blue, Tucson",
   "operator": "Developer per Pima County filings",
   "state": "AZ",
   "place": "Tucson (unincorporated Pima County)",
   "lat": 32.3,
   "lon": -110.95,
   "precision": "city",
   "kind": "facility",
   "status": "Construction reported underway since April 2026; city rules adopted Aug. 5, 2026",
   "mw": null,
   "mw_note": "Large-scale data-center rules adopted (6-1)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "project-midway-pinal",
   "name": "Project Midway, Pinal County",
   "operator": "Applicant per Pinal County filings",
   "state": "AZ",
   "place": "Pinal County",
   "lat": 33.0,
   "lon": -111.5,
   "precision": "county",
   "kind": "proposal",
   "status": "Comprehensive plan amendment reported approved Nov. 2025 (secondary report)",
   "mw": null,
   "mw_note": "About 215 acres",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "qts-phoenix-ii-mcdowell",
   "name": "QTS Phoenix II",
   "operator": "QTS Phoenix II, LLC",
   "state": "AZ",
   "place": "Phoenix (40th St. and McDowell Road)",
   "lat": 33.46,
   "lon": -111.99,
   "precision": "city",
   "kind": "proposal",
   "status": "Council item Dec. 13, 2023 (Ordinance S-50411)",
   "mw": null,
   "mw_note": "About 97.85 acres",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "sf-dc1-vienna",
   "name": "SF DC1 Vienna (Tysons)",
   "operator": "SF DC1 LLC",
   "state": "VA",
   "place": "Tysons (Fairfax County)",
   "lat": 38.92,
   "lon": -77.23,
   "precision": "city",
   "kind": "proposal",
   "status": "Applicant asked to defer special exception indefinitely (Oct. 2026)",
   "mw": null,
   "mw_note": "About 316,228 sq ft; 14.4 acres",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "stream-goodyear-campus",
   "name": "Stream Goodyear campus",
   "operator": "Stream Data Centers",
   "state": "AZ",
   "place": "Goodyear (2950 S. Litchfield Road)",
   "lat": 33.42,
   "lon": -112.36,
   "precision": "city",
   "kind": "facility",
   "status": "Seven buildings planned on 157+ acres; first two serving tenants (operator)",
   "mw": 280,
   "mw_note": "280 MW critical load at full build (operator); substation 480 MW (operator) vs 350 MW (2019 city release)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "vantage-az1-goodyear",
   "name": "Vantage AZ1 Goodyear",
   "operator": "Vantage Data Centers",
   "state": "AZ",
   "place": "Goodyear",
   "lat": 33.44,
   "lon": -112.37,
   "precision": "city",
   "kind": "facility",
   "status": "Operator release (2021); later reports describe five planned buildings",
   "mw": 160,
   "mw_note": "160 MW IT across three facilities (2021 operator release)",
   "verified": "dossier",
   "dossier": true
  },
  {
   "slug": "vantage-goodyear-phase-two",
   "name": "Vantage Goodyear Phase II",
   "operator": "Vantage Data Centers",
   "state": "AZ",
   "place": "Goodyear",
   "lat": 33.44,
   "lon": -112.37,
   "precision": "city",
   "kind": "facility",
   "status": "Topped out July 2023; operating date scheduled spring 2024",
   "mw": 176,
   "mw_note": "176 MW IT across three facilities (operator, July 2023); 160 MW in a 2021 release",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "vermaland-la-osa-pinal",
   "name": "Vermaland La Osa",
   "operator": "Vermaland LLC",
   "state": "AZ",
   "place": "Eloy (Pinal County)",
   "lat": 32.79,
   "lon": -111.56,
   "precision": "city",
   "kind": "proposal",
   "status": "Campus cut to 11 buildings after May 2026 opposition (ABC15, July 20, 2026); planning and zoning items on July 16 agenda",
   "mw": null,
   "mw_note": "3,300 acres; 11 buildings (was 59)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "forsyth-technology-campus-ga",
   "name": "Forsyth Technology Campus",
   "operator": "Developer named in state filings (H&H Timberlands owners)",
   "state": "GA",
   "place": "Forsyth (Monroe County)",
   "lat": 33.04,
   "lon": -83.94,
   "precision": "city",
   "kind": "facility",
   "status": "Rezoning approved by Forsyth city council, Feb. 2, 2026 (GPB); 1,600-acre timberland site",
   "mw": null,
   "mw_note": "State filings: $224M a year projected in city tax revenue; city water permit 4 MGD (about half projected need)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "project-camellia-effingham-ga",
   "name": "Project Camellia (OpenAI)",
   "operator": "OpenAI (developer per The Current; Octans GA LLC on DRI form)",
   "state": "GA",
   "place": "Rincon (Effingham County)",
   "lat": 32.3,
   "lon": -81.24,
   "precision": "city",
   "kind": "proposal",
   "status": "Announced July 22, 2026; DRI form submitted; four buildings on about 101 acres; launch projected 2028",
   "mw": 3200,
   "mw_note": "3.2 GW of Georgia Power supply, phased 2028–2032 (The Current); not an IT-load figure",
   "verified": "checked",
   "dossier": false
  },
  {
   "slug": "wallace-jackson-spalding-ga",
   "name": "Wallace Jackson Data Center Campus",
   "operator": "Wallace Jackson LLC",
   "state": "GA",
   "place": "Griffin (Spalding County)",
   "lat": 33.25,
   "lon": -84.27,
   "precision": "city",
   "kind": "facility",
   "status": "Proposed Jan. 2026 (AJC); county zoning approved Jan. 22, 2026 per IDCnova (secondary)",
   "mw": null,
   "mw_note": "AJC: $3.7B, 10 buildings, nearly 5M sq ft, about 190 acres; approved figure $3.9B (secondary)",
   "verified": "checked",
   "dossier": false
  },
  {
   "slug": "digital-realty-kokomo-in",
   "name": "Digital Realty Kokomo campus",
   "operator": "Digital Realty",
   "state": "IN",
   "place": "Kokomo (Howard County)",
   "lat": 40.49,
   "lon": -86.13,
   "precision": "city",
   "kind": "proposal",
   "status": "Proposed; site plan targets completion in 2033 (Baxtel, Oct. 16, 2026)",
   "mw": 1000,
   "mw_note": "1 GW IT capacity across three million sq ft on 476 acres (Baxtel, one source)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "bristolville-25-lordstown-oh",
   "name": "Bristolville 25 campus, Lordstown",
   "operator": "Bristolville 25 Developer LLC (Dublin, Ohio)",
   "state": "OH",
   "place": "Lordstown (Trumbull County)",
   "lat": 41.28,
   "lon": -80.53,
   "precision": "city",
   "kind": "proposal",
   "status": "Ohio Supreme Court ruled Oct. 20, 2026 that the village may pause review (LDS summary of the ruling)",
   "mw": null,
   "mw_note": "$3.6B, four three-story buildings, about 130 acres (Business Journal Daily via LDS)",
   "verified": "checked",
   "dossier": false
  },
  {
   "slug": "prologis-shelbyville-in",
   "name": "Prologis Shelbyville campus",
   "operator": "Prologis (no end user identified)",
   "state": "IN",
   "place": "Shelbyville (Shelby County)",
   "lat": 39.52,
   "lon": -85.77,
   "precision": "city",
   "kind": "proposal",
   "status": "Annexation and rezoning requested, Jan. 2026; Plan Commission and Council review; petition against with 2,100+ signatures",
   "mw": null,
   "mw_note": "Up to 13 buildings on about 576 acres after annexation (Construction Owners, Jan. 7, 2026)",
   "verified": "checked",
   "dossier": false
  },
  {
   "slug": "crane-pierce-township-oh",
   "name": "Crane Data Centers, Pierce Township",
   "operator": "Crane Data Centers (San Francisco)",
   "state": "OH",
   "place": "Pierce Township (Clermont County)",
   "lat": 39.02,
   "lon": -84.2,
   "precision": "city",
   "kind": "proposal",
   "status": "Proposed to Pierce Township zoning commission, Sept. 2026; township moratorium in place; trustees still to review",
   "mw": 300,
   "mw_note": "300 MW; three buildings on 300 acres beside the closed Beckjord plant (WVXU)",
   "verified": "checked",
   "dossier": false
  },
  {
   "slug": "google-lima-oh",
   "name": "Google Lima campus",
   "operator": "Google (identified by local leaders, Mar. 2026)",
   "state": "OH",
   "place": "American Township near Lima (Allen County)",
   "lat": 40.73,
   "lon": -84.15,
   "precision": "city",
   "kind": "proposal",
   "status": "Under state air-permit review; draft permit covers more than 100 diesel generators (WLZZ, one local source)",
   "mw": null,
   "mw_note": "$500M on more than 200 acres; about $50M in roadwork (WLZZ)",
   "verified": "checked",
   "dossier": false
  },
  {
   "slug": "lakeland-cleveland-oh",
   "name": "Lakeland Equity campus, Cleveland",
   "operator": "Lakeland Equity Group (end user undisclosed)",
   "state": "OH",
   "place": "Cleveland (Slavic Village)",
   "lat": 41.45,
   "lon": -81.62,
   "precision": "city",
   "kind": "proposal",
   "status": "Permit denied by the city, May 14, 2026 (Baxtel)",
   "mw": 150,
   "mw_note": "150 MW, three buildings, 300,000 sq ft on 35 acres; $1.6B (Baxtel)",
   "verified": "checked",
   "dossier": false
  },
  {
   "slug": "project-azalea-mcduffie-ga",
   "name": "Project Azalea",
   "operator": "Project Turbo LLC (linked developer)",
   "state": "GA",
   "place": "Thomson (McDuffie County)",
   "lat": 33.47,
   "lon": -82.5,
   "precision": "city",
   "kind": "proposal",
   "status": "Approved 4-1 by county commission, Mar. 2026; utility study says sufficient supply is not yet available (Baxtel)",
   "mw": 400,
   "mw_note": "Six buildings on 200 acres; 400 MW planned supply from Jefferson Energy; $1B (Baxtel)",
   "verified": "checked",
   "dossier": false
  },
  {
   "slug": "project-arrowhead-irwin-ga",
   "name": "Project Arrowhead, Irwin County",
   "operator": "Premier Data Center Development LLC",
   "state": "GA",
   "place": "Mystic area (Irwin County)",
   "lat": 31.59,
   "lon": -83.25,
   "precision": "city",
   "kind": "proposal",
   "status": "DRI application filed Apr. 2026; Georgia Power energy study underway; first phase targeted 2030",
   "mw": 1250,
   "mw_note": "Five buildings, 4.22M sq ft on about 1,000 acres; 1.25 GW; up to $6B (Baxtel)",
   "verified": "checked",
   "dossier": false
  },
  {
   "slug": "metter-canoochee-ga",
   "name": "Canoochee River RV Resort data center",
   "operator": "Canoochee River RV Resort, LLC",
   "state": "GA",
   "place": "Metter (Candler County)",
   "lat": 32.39,
   "lon": -82.05,
   "precision": "city",
   "kind": "proposal",
   "status": "DRI application filed Oct. 2026; county rezoning to PUD pending; completion targeted 2033",
   "mw": null,
   "mw_note": "Five buildings up to 250,000 sq ft each on 470 acres; two substations (Baxtel)",
   "verified": "checked",
   "dossier": false
  },
  {
   "slug": "berry-hill-pittsylvania-va",
   "name": "Berry Hill campus (STACK, Project Crossroads)",
   "operator": "STACK Infrastructure (end user unknown)",
   "state": "VA",
   "place": "Berry Hill, Pittsylvania County (Danville area)",
   "lat": 36.62,
   "lon": -79.42,
   "precision": "city",
   "kind": "proposal",
   "status": "Joint state and federal application filed Oct. 2026; permit decision expected by March 2027",
   "mw": 3000,
   "mw_note": "21 buildings over 15 years; up to 3,000 MW ceiling (not guaranteed); up to 7 MGD water; $100B (WDBJ, Oct. 26, 2026)",
   "verified": "checked",
   "dossier": false
  },
  {
   "slug": "jefferson-davis-ms",
   "name": "Big Woods Technology Park, Jefferson Davis County",
   "operator": "Eagle Rock Partners",
   "state": "MS",
   "place": "Jefferson Davis County",
   "lat": 31.6,
   "lon": -89.9,
   "precision": "county",
   "kind": "proposal",
   "status": "Planned; on-site gas generation needs Mississippi DEQ approval before operation (Planetizen, Oct. 4, 2026)",
   "mw": null,
   "mw_note": "$6B, roughly 2M sq ft; 1,000 temporary and 200 permanent jobs (Planetizen)",
   "verified": "checked",
   "dossier": false
  },
  {
   "slug": "taylor-technology-campus-tx",
   "name": "Taylor Technology Campus (Project Mustang)",
   "operator": "Big Watt Digital and PowerHouse Data Centers",
   "state": "TX",
   "place": "Taylor (Williamson County)",
   "lat": 30.57,
   "lon": -97.36,
   "precision": "city",
   "kind": "facility",
   "status": "Council approved unanimously, Oct. 8, 2026 (KUT)",
   "mw": null,
   "mw_note": "664 acres; no capacity stated in KUT (Oct. 9, 2026); $28.2M community investment estimate (developers)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "google-project-clydesdale-owasso-ok",
   "name": "Project Clydesdale",
   "operator": "Google (operator); Beale Infrastructure (developer)",
   "state": "OK",
   "place": "Unincorporated Tulsa County, near Owasso",
   "lat": 36.25,
   "lon": -95.82,
   "precision": "city",
   "kind": "facility",
   "status": "Under construction per Google and Beale release, Aug. 19, 2026",
   "mw": null,
   "mw_note": "506 acres; powered by PSO with a new onsite substation; capacity not stated",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "beltline-energy-okc-ok",
   "name": "Beltline Energy data center (Oklahoma City)",
   "operator": "Beltline Energy",
   "state": "OK",
   "place": "Oklahoma City, near I-40 and Frisco Road",
   "lat": 35.47,
   "lon": -97.73,
   "precision": "city",
   "kind": "proposal",
   "status": "Rezoning approved with conditions, Oct. 27, 2026; further agreements needed before construction",
   "mw": null,
   "mw_note": "Conditions cover water, electricity and noise; numeric limits not given (News 9)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "project-thunderbird-enid-ok",
   "name": "Project Thunderbird (Enid Data Center and Power Campus)",
   "operator": "Plainsman Holdings LLC",
   "state": "OK",
   "place": "Enid (Garfield County), four sites",
   "lat": 36.4,
   "lon": -97.88,
   "precision": "city",
   "kind": "proposal",
   "status": "Proposed; not approved; rezoning filed for two sites (News 9, Sept. 2026)",
   "mw": 2750,
   "mw_note": "2.75 GW IT load and 3.3 GW on-site gas generation (developer; News 9, Sept. 8, 2026)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "project-river-bradley-tn",
   "name": "Project River energy and data center campus",
   "operator": "Wright Brothers Construction",
   "state": "TN",
   "place": "West of Cleveland, Bradley County (west of I-75)",
   "lat": 35.2,
   "lon": -84.95,
   "precision": "city",
   "kind": "proposal",
   "status": "Rezoning and annexation into Cleveland submitted (Aug. 2026); offtaker not chosen",
   "mw": 1500,
   "mw_note": "$11.3B; 850 acres; 1,500 MW on-site generation; 360 MW TVA backup/peak requested (News 9, Aug. 26, 2026)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "kingsboro-edgecombe-nc",
   "name": "Energy Storage Solutions data center campus",
   "operator": "Energy Storage Solutions",
   "state": "NC",
   "place": "Rocky Mount area (Edgecombe County)",
   "lat": 35.94,
   "lon": -77.79,
   "precision": "city",
   "kind": "proposal",
   "status": "Zoning amended Nov. 2025; land sale pending county approval as of Nov. 2025 (WFAE)",
   "mw": 900,
   "mw_note": "$19B; 900 MW; 300-acre site per WFAE (a Baxtel summary gives 155 acres, not checked)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "microsoft-person-county-nc",
   "name": "Person County Mega Park data center",
   "operator": "Microsoft",
   "state": "NC",
   "place": "North of Roxboro (Person County)",
   "lat": 36.47,
   "lon": -78.98,
   "precision": "city",
   "kind": "proposal",
   "status": "Land bought Oct. 2024; permitting reportedly begins 2026 (Bisnow, Feb. 2026)",
   "mw": null,
   "mw_note": "About 1,350 acres (Bisnow); Baxtel summary says 1,385 (not checked); capacity not disclosed",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "whitefiber-yadkin-nc",
   "name": "WhiteFiber AI data center campus",
   "operator": "WhiteFiber",
   "state": "NC",
   "place": "Yadkin County",
   "lat": 36.13,
   "lon": -80.66,
   "precision": "county",
   "kind": "proposal",
   "status": "Acquisition agreed ($60M, close expected fall 2026); two-year county moratorium approved",
   "mw": 200,
   "mw_note": "60 MW initial; up to about 200 MW potential (WUNC, Aug. 19, 2026)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "microsoft-mount-pleasant-expansion-wi",
   "name": "Microsoft Mount Pleasant expansion (15 proposed data centers)",
   "operator": "Microsoft",
   "state": "WI",
   "place": "Mount Pleasant (Racine County), former Foxconn site",
   "lat": 42.72,
   "lon": -87.9,
   "precision": "city",
   "kind": "proposal",
   "status": "Planning commission recommended conditional approval, Jan. 2026",
   "mw": null,
   "mw_note": "15 data centers in two campuses, over $13B (WPR, Jan. 20, 2026); no energy estimate published",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "google-new-florence-mo",
   "name": "Google Montgomery County campus",
   "operator": "Google",
   "state": "MO",
   "place": "New Florence (Montgomery County)",
   "lat": 38.9,
   "lon": -91.52,
   "precision": "city",
   "kind": "proposal",
   "status": "Announced May 21, 2026",
   "mw": null,
   "mw_note": "$15B statewide; Google's 1 GW+ is generation contracted in Missouri, not campus load (release)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "nebius-independence-mo",
   "name": "Nebius Independence campus",
   "operator": "Nebius",
   "state": "MO",
   "place": "Independence (Jackson County)",
   "lat": 39.09,
   "lon": -94.42,
   "precision": "city",
   "kind": "facility",
   "status": "Broke ground May 2026; first phase expected mid-2027 (chairman)",
   "mw": 800,
   "mw_note": "800 MW (Axios, Sept. 25, 2026); 1.2 GW in an earlier source",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "google-project-mica-kansas-city-mo",
   "name": "Google Project Mica",
   "operator": "Google",
   "state": "MO",
   "place": "Kansas City (Northland)",
   "lat": 39.28,
   "lon": -94.61,
   "precision": "city",
   "kind": "facility",
   "status": "Google confirmed Feb. 12, 2026; Port KC bonds up to $10B authorized",
   "mw": 500,
   "mw_note": "Up to 500 MW (Axios); project materials cite nearly 700 MW supply",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "lambda-mayes-county-ok",
   "name": "Lambda Mayes County campus",
   "operator": "Lambda",
   "state": "OK",
   "place": "Chouteau (Mayes County)",
   "lat": 36.2,
   "lon": -95.38,
   "precision": "city",
   "kind": "proposal",
   "status": "Announced Sept. 27, 2026; timeline not released",
   "mw": null,
   "mw_note": "Not stated; company says it will pay all energy costs",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "google-muskogee-county-ok",
   "name": "Google Muskogee County campuses",
   "operator": "Google",
   "state": "OK",
   "place": "Summit and Council Hill (Muskogee County)",
   "lat": 35.66,
   "lon": -95.36,
   "precision": "county",
   "kind": "proposal",
   "status": "Announced Nov. 20, 2025; OG&E contracts; campus size not stated",
   "mw": null,
   "mw_note": "600 MW of new solar PPAs (not campus load)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "port-washington-vantage-wi",
   "name": "Vantage Lighthouse campus",
   "operator": "Vantage Data Centers",
   "state": "WI",
   "place": "Port Washington (Ozaukee County)",
   "lat": 43.39,
   "lon": -87.88,
   "precision": "city",
   "kind": "facility",
   "status": "Being constructed (DNR); air permits issued June 12, 2026; phases through 2034",
   "mw": 1300,
   "mw_note": "1.3 GW (city and WPR figure)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "microsoft-caledonia-wi-withdrawn",
   "name": "Microsoft Caledonia site",
   "operator": "Microsoft",
   "state": "WI",
   "place": "Caledonia (Racine County)",
   "lat": 42.77,
   "lon": -87.88,
   "precision": "city",
   "kind": "proposal",
   "status": "Withdrawn Oct. 8, 2025 after community opposition; company seeking another site",
   "mw": null,
   "mw_note": "244 acres; no MW stated",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "metrobloks-liberty-mo",
   "name": "Metrobloks Liberty campus",
   "operator": "Metrobloks",
   "state": "MO",
   "place": "Liberty (Clay County)",
   "lat": 39.25,
   "lon": -94.42,
   "precision": "city",
   "kind": "proposal",
   "status": "Announced Mar. 24, 2026; construction schedule not stated",
   "mw": null,
   "mw_note": "$1.4B; 568,800 sq ft; power capacity not stated",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "google-franklin-township-indianapolis-in",
   "name": "Google Franklin Township proposal",
   "operator": "Google",
   "state": "IN",
   "place": "Indianapolis (Franklin Township)",
   "lat": 39.68,
   "lon": -86.07,
   "precision": "city",
   "kind": "proposal",
   "status": "Rezoning petition withdrawn Sept. 22, 2025",
   "mw": null,
   "mw_note": "468 acres rezoning; no MW stated",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "project-bluestem-tonganoxie-ks",
   "name": "Project Bluestem",
   "operator": "Cloverleaf Infrastructure",
   "state": "KS",
   "place": "Tonganoxie (Leavenworth County)",
   "lat": 39.1,
   "lon": -95.09,
   "precision": "city",
   "kind": "proposal",
   "status": "Under county review; no permit application filed as of Aug. 2026; moratorium expired",
   "mw": 1200,
   "mw_note": "1.2 GW with on-site gas plant (KSHB)",
   "verified": "checked",
   "dossier": true
  },
  {
   "slug": "amazon-montgomery-county-mo",
   "name": "Amazon data center campus",
   "operator": "Amazon",
   "state": "MO",
   "place": "Montgomery County, eastern Missouri",
   "lat": 38.98,
   "lon": -91.5,
   "precision": "county",
   "kind": "proposal",
   "status": "Announced June 15, 2026; groundbreaking and opening dates not released",
   "mw": null,
   "mw_note": "$10B; about 400 direct jobs; Amazon pays 100% of electric service costs (Missourinet, June 15, 2026)",
   "verified": "checked",
   "dossier": true
  }
 ]
}