Microsoft Mount Pleasant expansion — Wisconsin

Microsoft's proposed expansion in Mount Pleasant would add 15 data centers in two campuses on land it bought in 2024. The planning commission recommended approval with conditions, and the company has not published an energy estimate.

At a glance

Developer / operator
Microsoft
Jurisdiction
Village of Mount Pleasant, Racine County, Wisconsin
Campuses
Durand Avenue (nine data centers, 791 acres); International Drive (six data centers, about 530 acres)
Investment
More than $13 billion across the two campuses
Water
Up to 8.4 million gallons a year at full buildout, per Microsoft's earlier statements
Status
Planning commission recommended approval with conditions, January 2026

What the sources establish

  • Microsoft proposes 15 more data centers in Mount Pleasant as part of two new campuses worth more than $13 billion, according to Wisconsin Public Radio. [1]
  • The Durand Avenue initial phase shows nine data centers and a 96,000-square-foot office on a 791-acre parcel, with a taxable value above $7.97 billion. [1]
  • The International Drive initial phase shows six data centers and a 74,000-square-foot office across about 530 acres, with a taxable value above $5.3 billion. [1]
  • The planning commission recommended approval as long as Microsoft meets several conditions, including a traffic analysis and state and local water-use rules. [1]
  • Both developments would sit in tax increment financing districts. The village estimates about $45 million a year from Durand and about $30 million a year from International Drive once district debts are paid. [1]
  • Microsoft has previously said its Mount Pleasant data centers would use up to 8.4 million gallons a year at full buildout, and a spokesperson said the expansion is expected to fit within that estimate. [1]
  • A Microsoft spokesperson said an estimate of the proposed data centers' energy use was not available at the time. [1]
  • If the plans are approved, the company may submit engineering plans, followed by building permit applications, before construction begins. [1]

Conflicts. Energy: a secondary summary, not opened here, gives 900 MW for the expansion with existing facilities. Microsoft said no energy estimate was available, so this page does not use that figure. Water: the spokesperson expects the expansion to fit the 8.4 million gallon estimate, and says additional local approval would be needed if it does not.

Timeline

  1. Jan. 20, 2026 — Wisconsin Public Radio reports Microsoft's proposal and the two site plans.
  2. Jan. 21, 2026 — Planning commission meeting scheduled at village hall, 1 p.m. (WPR).

What this page does not establish

  • Whether the planning commission's conditions were met and whether the village board has voted.
  • Megawatt demand and the energy estimate.
  • The construction schedule.
  • Whether the water estimate covers the expansion.

What to check next

  1. Village of Mount Pleasant plan commission minutes and staff report for Jan. 21, 2026.
  2. Village board actions on the site plans and the TIF districts.
  3. We Energies rate filings for the large-customer rate that WPR mentions.
  4. Microsoft's water-use reporting for the Mount Pleasant campuses.