At a glance
- Developer / operator
- Microsoft
- Jurisdiction
- Village of Mount Pleasant, Racine County, Wisconsin
- Campuses
- Durand Avenue (nine data centers, 791 acres); International Drive (six data centers, about 530 acres)
- Investment
- More than $13 billion across the two campuses
- Water
- Up to 8.4 million gallons a year at full buildout, per Microsoft's earlier statements
- Status
- Planning commission recommended approval with conditions, January 2026
What the sources establish
- Microsoft proposes 15 more data centers in Mount Pleasant as part of two new campuses worth more than $13 billion, according to Wisconsin Public Radio. [1]
- The Durand Avenue initial phase shows nine data centers and a 96,000-square-foot office on a 791-acre parcel, with a taxable value above $7.97 billion. [1]
- The International Drive initial phase shows six data centers and a 74,000-square-foot office across about 530 acres, with a taxable value above $5.3 billion. [1]
- The planning commission recommended approval as long as Microsoft meets several conditions, including a traffic analysis and state and local water-use rules. [1]
- Both developments would sit in tax increment financing districts. The village estimates about $45 million a year from Durand and about $30 million a year from International Drive once district debts are paid. [1]
- Microsoft has previously said its Mount Pleasant data centers would use up to 8.4 million gallons a year at full buildout, and a spokesperson said the expansion is expected to fit within that estimate. [1]
- A Microsoft spokesperson said an estimate of the proposed data centers' energy use was not available at the time. [1]
- If the plans are approved, the company may submit engineering plans, followed by building permit applications, before construction begins. [1]
Conflicts. Energy: a secondary summary, not opened here, gives 900 MW for the expansion with existing facilities. Microsoft said no energy estimate was available, so this page does not use that figure. Water: the spokesperson expects the expansion to fit the 8.4 million gallon estimate, and says additional local approval would be needed if it does not.
Timeline
- Jan. 20, 2026 — Wisconsin Public Radio reports Microsoft's proposal and the two site plans.
- Jan. 21, 2026 — Planning commission meeting scheduled at village hall, 1 p.m. (WPR).
What this page does not establish
- Whether the planning commission's conditions were met and whether the village board has voted.
- Megawatt demand and the energy estimate.
- The construction schedule.
- Whether the water estimate covers the expansion.
What to check next
- Village of Mount Pleasant plan commission minutes and staff report for Jan. 21, 2026.
- Village board actions on the site plans and the TIF districts.
- We Energies rate filings for the large-customer rate that WPR mentions.
- Microsoft's water-use reporting for the Mount Pleasant campuses.