At a glance
- Operator
- Stream Data Centers
- Address
- 2950 S. Litchfield Road, Goodyear, AZ 85338 (operator)
- Land
- 157 acres (city release, 2019)
- Building
- 418,000 sq ft acquired (city release, 2019)
- Power
- Substation: 350 MW (city, 2019) vs 480 MW (operator)
What the sources establish
- Stream's campus page describes a seven-building Goodyear campus at 2950 S. Litchfield Road. [1]
- The city's release (February 15, 2019) says Stream acquired a 418,000 sq ft facility on 157 acres. [2]
- The city release says the redeveloped facility will hold about 50 MW of critical load at full build-out, fully operational in the first quarter of 2020. [2]
- The operator says its dedicated APS substation has an ultimate power capacity of 480 MW. [1]
- The city release says the substation will be constructed by APS with an ultimate capacity of 350 MW. [2]
Timeline
- 2019-02-15 — City announces Stream's acquisition.
- 2020-Q1 — Projected operational date (city release).
Conflicts and corrections
The substation capacity is 350 MW in the city's 2019 release and 480 MW on Stream's current page. We have not found a source that explains the change.
What this page does not establish
- Which substation figure is current.
- Current operating status of each building.
- Water source and generator count.
What to check next
- Ask Stream and APS which substation figure is current.
- Pull the Goodyear permit history for the site.
- Check the 2020 operational date against the current status.