At a glance
- Operator
- Compass Datacenters
- Jurisdiction
- City of Goodyear, Arizona
- Location
- Northwest corner of Bullard Avenue and Yuma Road
- Land
- 225 acres (2019 city release)
- Capacity
- 212 MW (Compass market page); 350 MW at build-out (2019 city release)
What the sources establish
- The city council approved an agreement with Compass on July 8, 2019, for a campus on 225 acres at the northwest corner of Bullard Avenue and Yuma Road. [2]
- The first phase was projected to deliver 72 MW of IT load and finish in the fourth quarter of 2019. [2]
- At full build-out, the city release says eight data centers totaling over 1.8 million square feet, capable of 350 MW. [2]
- Compass's market page says it is developing a 212 MW campus in Goodyear and a 108 MW campus in El Mirage. [1]
Timeline
- 2019-07-08 — Goodyear council approves the Compass agreement.
- 2019-Q4 — Projected completion of the first phase (2019 release).
Conflicts and corrections
The city's 2019 build-out (350 MW) and Compass's current listing (212 MW) describe different scopes. We have not found a source that explains the change.
What this page does not establish
- Whether the first phase was completed on the 2019 schedule.
- Which buildings are built, under construction, or planned.
- Current approved capacity and power service.
What to check next
- Ask Compass for the current Goodyear phase list and status.
- Check Goodyear's development agreement and any amendments.
- Look for APS service or substation filings tied to the campus.