Arizona facility dossier · sources checked 2026-11-08

Compass Datacenters — Goodyear campus

Goodyear's July 2019 release describes Compass's campus on 225 acres at Bullard Avenue and Yuma Road: a first phase of 72 MW IT load and eight buildings with 350 MW at full build-out. Compass's current market page gives a different figure, a 212 MW Goodyear campus, so the two need to be reconciled.

At a glance

Operator
Compass Datacenters
Jurisdiction
City of Goodyear, Arizona
Location
Northwest corner of Bullard Avenue and Yuma Road
Land
225 acres (2019 city release)
Capacity
212 MW (Compass market page); 350 MW at build-out (2019 city release)

What the sources establish

  • The city council approved an agreement with Compass on July 8, 2019, for a campus on 225 acres at the northwest corner of Bullard Avenue and Yuma Road. [2]
  • The first phase was projected to deliver 72 MW of IT load and finish in the fourth quarter of 2019. [2]
  • At full build-out, the city release says eight data centers totaling over 1.8 million square feet, capable of 350 MW. [2]
  • Compass's market page says it is developing a 212 MW campus in Goodyear and a 108 MW campus in El Mirage. [1]

Timeline

  1. 2019-07-08 — Goodyear council approves the Compass agreement.
  2. 2019-Q4 — Projected completion of the first phase (2019 release).

Conflicts and corrections

The city's 2019 build-out (350 MW) and Compass's current listing (212 MW) describe different scopes. We have not found a source that explains the change.

What this page does not establish

  • Whether the first phase was completed on the 2019 schedule.
  • Which buildings are built, under construction, or planned.
  • Current approved capacity and power service.

What to check next

  1. Ask Compass for the current Goodyear phase list and status.
  2. Check Goodyear's development agreement and any amendments.
  3. Look for APS service or substation filings tied to the campus.