WHY IS LIFE SO HARD?Data-center field guide
Arizona facility dossier · sources checked 2026-11-08

Aligned PHX-13 — Glendale campus

Glendale's city release says Aligned broke ground on PHX-13 on April 15, 2025: a 72 MW building and one of four planned facilities on a 100-acre campus, served by a new 230 kV APS line.

At a glance

Operator
Aligned Data Centers
Jurisdiction
City of Glendale, Arizona
Status
Under construction (groundbreaking April 15, 2025)
Capacity
72 MW (city release)
Campus
100 acres, four planned facilities

What the sources establish

  • Aligned broke ground on PHX-13, a 72 MW data center that is one of four planned facilities on a 100-acre Glendale campus. [1]
  • The project will include a new 230 kV transmission line from Arizona Public Service to serve the campus. [1]
  • Aligned says PHX-13 will use its Delta³ air-cooling arrays and a closed-loop cooling system that recycles water. [1]
  • The city release says the former rose farm site's water use will fall by more than 73% annually, and that Aligned retained the site's unused well rights. [1]

Timeline

  1. 2025-04-15 — Groundbreaking on PHX-13 (city release, published 2025-04-17).

Conflicts and corrections

The 73% water reduction is the city's description of the site redevelopment and is not a measured figure for the building.

What this page does not establish

  • Completion date and energization date for PHX-13.
  • Status of the other three planned facilities on the campus.
  • The source and volume of the water used during construction and operation.

What to check next

  1. Find Glendale's site plan and building permits for PHX-13.
  2. Check the APS filing for the 230 kV line.
  3. Confirm whether the closed-loop cooling and the well rights are in the approved plan.