At a glance
- Operator
- CloudHQ
- Market
- Ashburn, Loudoun County, Virginia
- Coordinates
- 39.01015, -77.46270 (operator page)
- Capacity
- 756 MW available critical IT load; 1,256 MW total (operator page)
- Target
- Ready for service within 20 months (operator page)
What the sources establish
- CloudHQ's LC Campus page lists about 8.5 million square feet, 756 MW of available critical IT load, 1,256 MW total critical IT load, and ready for service within 20 months. [1]
- Loudoun County's Board approved Phase 1 of its data-center zoning changes on March 18, 2025, which designate data centers as a conditional or special-exception (SPEX) use in certain areas. [2]
- The county adopted a Grandfathering Resolution for data-center applications accepted before February 12, 2025. [2]
Timeline
- 2025-02-12 — Cutoff date in the county's Grandfathering Resolution.
- 2025-03-18 — Loudoun County Board approves Phase 1 of data-center zoning changes.
Conflicts and corrections
The operator's figures are marketing capacity figures. The county's record does not state the campus's approval status.
What this page does not establish
- Whether the LC Campus is grandfathered under the county's February 12, 2025 cutoff.
- Whether a special exception has been filed or approved.
- Current construction status.
What to check next
- Check Loudoun County's land-use records for the LC Campus parcel and any special-exception application.
- Read the county's Grandfathering Resolution against the project's application date.
- Confirm the megawatt figures with the county's submitted plans.