Iron Mountain AZP-2

Iron Mountain's AZP-2 page describes up to 48 MW of critical IT load across 547,000 sq ft on the same 39-acre campus as AZP-1, in data halls of up to 6 MW each.

At a glance

Operator
Iron Mountain
Location
Same 39-acre campus as AZP-1, east of downtown Phoenix
Building
547,000 sq ft (operator page)
Capacity
Up to 48 MW critical IT load (operator page)
Data halls
21,000 sq ft each, up to 6 MW flexible density

What the sources establish

  • Iron Mountain says AZP-2 delivers up to 48 MW of critical IT load across 547,000 sq ft on a 39-acre campus. [1]
  • Each 21,000 sq ft data hall supports up to 6 MW of flexible density. [1]
  • The page says AZP-2 is the first BREEAM design-certified data center in North America, and that its power is 100% matched renewable energy. [1]
  • The operator's Phoenix overview lists AZP-2 among the four operational Phoenix-area facilities. [2]

Conflicts and corrections

BREEAM design certification is a design-stage rating; it does not show the building's operating performance.

What this page does not establish

  • Construction and energization dates.
  • Whether the 48 MW figure is the full build-out or current capacity.
  • Permit history for the campus.

What to check next

  1. Pull the campus's permit records for AZP-2.
  2. Confirm the operational date with the operator.
  3. Compare the 48 MW figure with AZP-1's 41 MW on the same campus.