WHY IS LIFE SO HARD?Data-center field guide
Arizona facility dossier · sources checked 2026-11-08

Edged Energy PHX01-1 — Mesa

A Mesa facility listed as a 36 MW, two-story building using waterless cooling. Separate listings give a different size and site for a project near Loop 202 and Warner Road, and the two are not yet matched.

At a glance

Operator
Edged Energy (listing)
Jurisdiction
City of Mesa, Arizona
Power
36 MW (listing)
Building and land
Conflicting: about 210,000 sq ft on 12 acres (PHX01-1) vs. 79,200 sq ft on 14 acres (near Loop 202 and Warner Road)
Status
Listed as launched April 2026; no permit record retrieved

What the sources establish

  • A listing describes Edged Energy's PHX01-1 as a 36 MW, two-story data center of about 210,000 square feet on a 12-acre site in Mesa, launched in April 2026 with waterless cooling for high-density AI workloads. [1]
  • Another listing says Edged Energy is building a 79,200-square-foot data center on a 14-acre site near the Loop 202 freeway and Warner Road. [2]
  • A separate Edged Energy listing near EdgeConneX's Mesa campus carries a 'PHX11' name at a nearby address; the overlap is recorded on the EdgeConneX PHX11 page and is unresolved. [1]

Conflicts. Building size is about 210,000 sq ft in one listing and 79,200 sq ft in another, and acreage is 12 and 14. It is not confirmed that the two listings describe the same project. The 79,200 sq ft figure also matches EdgeConneX's Tempe PHX01 building, which may indicate a listing error.

Timeline

  1. Apr. 2026 — Listing states the PHX01-1 facility was launched (listing data).

What this page does not establish

  • Whether the 36 MW figure is planned or operating capacity.
  • Which of the two listed projects, if either, is the one approved by Mesa.
  • Permit, utility and water records.

What to check next

  1. Mesa planning and building-permit records under Edged Energy's name.
  2. The utility's service agreement for the 36 MW figure.
  3. The EdgeConneX PHX11 page's unresolved address overlap.