At a glance
- Developer
- Crusoe
- Tenants
- Oracle and OpenAI (reported lease)
- Jurisdiction
- Abilene, Texas (Taylor County area)
- Capacity
- 1.2 GW for the OpenAI and Oracle campus; 2.1 GW with planned Microsoft buildings (AP)
- Status
- First two buildings operational (Sept. 2025 report); later buildings in progress; disputes reported in March 2026
What the sources establish
- Crusoe's Abilene campus is leased to Oracle and OpenAI and is described as the first Stargate location. [6] [1]
- Crusoe reported the first two buildings operational in September 2025, totaling 980,000 sq ft and more than 200 MW of IT capacity. [2]
- The planned site is 1.2 GW and about 4 million sq ft across the full campus. [1] [2]
- A November 2025 report says Crusoe topped out the eighth and final building. [1]
- AP reported on March 27, 2026 that Crusoe is working with Microsoft on two new buildings and a 900 MW on-site power plant beside the campus, after OpenAI declined to pursue that expansion. With them, the site would total 10 buildings and 2.1 GW. [3]
- AP describes the existing 350 MW gas-fired plant attached to the OpenAI and Oracle project as smaller than the planned 900 MW Microsoft plant. [3]
- Oracle called reports of problems at the site 'false and incorrect'. Bloomberg later corrected a report: the expansion lease is not moving ahead, while the separate 4.5 GW Oracle-OpenAI agreement remains on track. [4]
- Crusoe's expansion financing was reported at $11.6 billion, with Blue Owl and Primary Digital Infrastructure co-sponsoring later buildings. [5]
Conflicts. Start date: June 2024 in one report and July 2024 in another. Capacity: 1.2 GW for the OpenAI and Oracle campus, but 2.1 GW once the Microsoft buildings are counted (AP). Completion: mid-2026 in one report and end-2026 in another.
Timeline
- June–July 2024 — Construction begins (reports differ).
- Mar. 2025 — Second phase announced, bringing the campus to about 4 million sq ft.
- Sept. 2025 — First two buildings reported operational.
- Nov. 2025 — Final building reported topped out.
- Mar. 2026 — Microsoft reported to take over two new buildings and an on-site power plant; Oracle disputes problem reports.
What this page does not establish
- Power: a 350 MW gas-fired plant attached to the OpenAI and Oracle project, and a 900 MW plant planned for the Microsoft buildings (AP, citing Crusoe).
- Whether the Microsoft buildings are part of the same campus permit.
- Current operating capacity across all buildings.
What to check next
- Taylor County and City of Abilene permit records.
- ERCOT and utility interconnection filings for the campus.
- Crusoe and Oracle statements on the completion schedule.