Approval timeline

Data centers in Goodyear, Arizona: approvals

Dated approvals, rezonings, and project milestones compiled from the source-linked dossier pages for this area.

Data center approvals and timelines: Goodyear, Arizona

6 records in Goodyear, Arizona. 6 have dated entries compiled from their dossier pages. Each entry links to its dossier and the sources listed there.

This page collects dated entries already in the dossier pages. It does not replace checking the city, county, or state record. Permit portals, agendas, and minutes are still to be checked for each record.

Compass Goodyear campus

2019 city release; status not confirmed

2019-07-08 — Goodyear council approves the Compass agreement. 2019-Q4 — Projected completion of the first phase (2019 release).

Microsoft El Mirage campus

Announced July 30, 2019; construction not confirmed

2019-07-30 — Microsoft announces the El Mirage and Goodyear campuses.

Microsoft Goodyear campus

Announced July 30, 2019; construction not confirmed

2019-07-30 — Microsoft announces Goodyear campus.

Stream Goodyear campus

Seven buildings planned on 157+ acres; first two serving tenants (operator)

2019-02-15 — City announces Stream's acquisition. 2020-Q1 — Projected operational date (city release). 2020 — Phoenix I launches: 40 MW of IT capacity in 418,000 sq ft. [3] 2024-08 — Second building on the Goodyear campus is topped out. [3] 2025 — Operator-linked listing says Phoenix II opened. Not confirmed by a primary source. [6] 2026-01-31 — Satellite-based tracker estimates major construction finished on AI building 1 (estimate, not a company statement). [5]

Vantage AZ1 Goodyear

Operator release (2021); later reports describe five planned buildings

2021-11 — Vantage announces its first Goodyear building topped out, described as 32 MW in one trade report and 16 MW in another. [6] [7] 2024-spring — Phase II scheduled to be operational (operator news). 2025 — Third building (AZ13) completed; the contractor says it is the third of five planned buildings, and Baxtel lists it as built in 2025. [3] [5] 2026 (expected summer) — AZ14, a 64 MW building, is topped out and expected to complete in summer 2026, per the general contractor. [3] Planned — AZ15, a 48 MW building in conceptual design (Corgan), listed as under construction for 2028 by Baxtel. [4] [5]

Vantage Goodyear Phase II

Topped out July 2023; operating date scheduled spring 2024

2024-spring — Phase II scheduled to be operational. unknown — Topping-out milestone (operator news; date not retrieved).

Still to check

Planning and zoning agendas, council minutes, building permits, and utility service agreements for each record above. Add the date and source when an entry is confirmed.