Approval timeline

Data centers in Marana, Arizona: approvals

Dated approvals, rezonings, and project milestones compiled from the source-linked dossier pages for this area.

Data center approvals and timelines: Marana, Arizona

3 records in Marana, Arizona. 1 have dated entries compiled from their dossier pages. Each entry links to its dossier and the sources listed there.

This page collects dated entries already in the dossier pages. It does not replace checking the city, county, or state record. Permit portals, agendas, and minutes are still to be checked for each record.

Luckett Road North Data Center

Town Council approval in January 2026

No dated approval or permit entries are in this record yet. Check the local agenda and permit portal.

Luckett Road South Data Center

Town Council approval in January 2026

No dated approval or permit entries are in this record yet. Check the local agenda and permit portal.

Luckett Road, Marana

Town Council rezoning approved Jan. 6, 2026; referendum petitions rejected; litigation

2025-12-10 — Planning Commission recommends rezoning. 2026-01-06 — Town Council approves the rezoning of two parcels unanimously. [3] 2026-02-10 — Residents submit referendum petitions with more than 2,800 signatures to overturn the rezoning. [4] 2026-02 — The town rejects the petitions; residents and the developer, Beale Infrastructure, later file separate lawsuits (reported Feb. 20 and Mar. 25, 2026). [5]

Still to check

Planning and zoning agendas, council minutes, building permits, and utility service agreements for each record above. Add the date and source when an entry is confirmed.