WHY IS LIFE SO HARD?Data-center field guide
AR dossier · checked Nov. 8, 2026

Willowbend Capital data-center complex

Little Rock (Pulaski County) · USACE received a Clean Water Act permit application in April 2026

Short answer

Willowbend Capital data-center complex is a documented proposed data-center project in Little Rock (Pulaski County). USACE received a Clean Water Act permit application in April 2026

At a glance

Developer / operator
Willowbend Capital LLC
Location
Little Rock (Pulaski County), AR
Public status
USACE received a Clean Water Act permit application in April 2026
Scale
Five-building complex; likely more than 100 MW according to the application
Map position
Campus-area locator, not a parcel boundary

What the sources establish

  • The listed public documents identify a data-center project or related permit process in this area. [1]
  • Current public status: USACE received a Clean Water Act permit application in April 2026 [1] [2]
  • Reported scale: Five-building complex; likely more than 100 MW according to the application [1]

What this page does not establish

  • Exact building entrances, final construction dates, or a final end user unless expressly named in the sources.
  • Annual water consumption, generator details, or final utility terms.
  • Whether later permits, votes, appeals, or withdrawals changed the project after the check date.

What to check next

  1. New county or city planning agendas, permits, and development agreements.
  2. State and federal air, water, wetland, and utility records.
  3. Developer notices that distinguish a proposal from active construction or operation.