WHY IS LIFE SO HARD?Data-center field guide
GA dossier · sources checked Nov. 8, 2026

Project Azalea

Thomson (McDuffie County) · Approved 4-1 by county commission, Mar. 2026; utility study says sufficient supply is not yet available (Baxtel)

Short answer

The currently checked public record identifies this as Project Azalea in Thomson (McDuffie County), GA. Current public-status summary: Approved 4-1 by county commission, Mar. 2026; utility study says sufficient supply is not yet available (Baxtel).

At a glance

Location
Thomson (McDuffie County), GA
Developer / operator
Project Turbo LLC (linked developer)
Public status
Approved 4-1 by county commission, Mar. 2026; utility study says sufficient supply is not yet available (Baxtel)
Scale
Six buildings on 200 acres; 400 MW planned supply from Jefferson Energy; $1B (Baxtel)
Map position
City-area pin; not a parcel boundary.

What the sources establish

  • The currently checked public record identifies this as Project Azalea in Thomson (McDuffie County), GA. [1] [2]
  • Current public-status summary: Approved 4-1 by county commission, Mar. 2026; utility study says sufficient supply is not yet available (Baxtel). [1] [2]
  • Capacity / scale note: Six buildings on 200 acres; 400 MW planned supply from Jefferson Energy; $1B (Baxtel). [1] [2]

What this page does not establish

  • Exact building count, final load, and construction sequence unless stated in the listed documents.
  • Annual water use, generator configuration, or utility agreement terms unless separately disclosed.
  • Whether an approval, proposal, or court decision has changed after the sources were checked.

What to check next

  1. New planning-agenda, permit, zoning, and utility filings from the relevant jurisdiction.
  2. Air, water, and wetlands permits where applicable.
  3. Developer announcements that distinguish a proposal from construction or operation.