Short answer
The currently checked public record identifies this as Project Arrowhead, Irwin County in Mystic area (Irwin County), GA. Current public-status summary: DRI application filed Apr. 2026; Georgia Power energy study underway; first phase targeted 2030.
At a glance
- Location
- Mystic area (Irwin County), GA
- Developer / operator
- Premier Data Center Development LLC
- Public status
- DRI application filed Apr. 2026; Georgia Power energy study underway; first phase targeted 2030
- Scale
- Five buildings, 4.22M sq ft on about 1,000 acres; 1.25 GW; up to $6B (Baxtel)
- Map position
- City-area pin; not a parcel boundary.
What the sources establish
- The currently checked public record identifies this as Project Arrowhead, Irwin County in Mystic area (Irwin County), GA. [1] [2]
- Current public-status summary: DRI application filed Apr. 2026; Georgia Power energy study underway; first phase targeted 2030. [1] [2]
- Capacity / scale note: Five buildings, 4.22M sq ft on about 1,000 acres; 1.25 GW; up to $6B (Baxtel). [1] [2]
What this page does not establish
- Exact building count, final load, and construction sequence unless stated in the listed documents.
- Annual water use, generator configuration, or utility agreement terms unless separately disclosed.
- Whether an approval, proposal, or court decision has changed after the sources were checked.
What to check next
- New planning-agenda, permit, zoning, and utility filings from the relevant jurisdiction.
- Air, water, and wetlands permits where applicable.
- Developer announcements that distinguish a proposal from construction or operation.