Project Arrowhead, Irwin County

Mystic area (Irwin County) · DRI application filed Apr. 2026; Georgia Power energy study underway; first phase targeted 2030

Short answer

The currently checked public record identifies this as Project Arrowhead, Irwin County in Mystic area (Irwin County), GA. Current public-status summary: DRI application filed Apr. 2026; Georgia Power energy study underway; first phase targeted 2030.

At a glance

Location
Mystic area (Irwin County), GA
Developer / operator
Premier Data Center Development LLC
Public status
DRI application filed Apr. 2026; Georgia Power energy study underway; first phase targeted 2030
Scale
Five buildings, 4.22M sq ft on about 1,000 acres; 1.25 GW; up to $6B (Baxtel)
Map position
City-area pin; not a parcel boundary.

What the sources establish

  • The currently checked public record identifies this as Project Arrowhead, Irwin County in Mystic area (Irwin County), GA. [1] [2]
  • Current public-status summary: DRI application filed Apr. 2026; Georgia Power energy study underway; first phase targeted 2030. [1] [2]
  • Capacity / scale note: Five buildings, 4.22M sq ft on about 1,000 acres; 1.25 GW; up to $6B (Baxtel). [1] [2]

What this page does not establish

  • Exact building count, final load, and construction sequence unless stated in the listed documents.
  • Annual water use, generator configuration, or utility agreement terms unless separately disclosed.
  • Whether an approval, proposal, or court decision has changed after the sources were checked.

What to check next

  1. New planning-agenda, permit, zoning, and utility filings from the relevant jurisdiction.
  2. Air, water, and wetlands permits where applicable.
  3. Developer announcements that distinguish a proposal from construction or operation.