At a glance
- Operator
- CyrusOne
- Jurisdiction
- City of Chandler, Arizona
- Routine runs
- Weekdays, 9 a.m. to 5 p.m. (no-load runs)
- Scheduled extended test
- August 11, 2026, 7 a.m. to 7 p.m.
What the sources establish
- CyrusOne's Chandler page says routine no-load generator runs happen on weekdays between 9 a.m. and 5 p.m. [1]
- The page lists dated test runs from 7 a.m. to 7 p.m. on April 23, 2025, December 18, 2025, January 22, 2026, February 5, 2026, May 27, 2026, and August 11, 2026. [1]
- The May 2026 run schedule was cut from eight days to four days, with runs from May 27 to June 10, 2026, to support a new substation. [1]
- Chandler's ordinance sets routine generator maintenance and testing time limits, including a notification protocol. [2]
Timeline
- 2025-04-23 — Generator test run (substation work).
- 2025-12-18 — Generator test run (substation work).
- 2026-01-22 — Generator test run (substation work).
- 2026-02-05 — Generator test run (substation work).
- 2026-05-27 — Generator runs start; schedule cut to four days ending 2026-06-10.
- 2026-08-11 — Generator test run for required substation maintenance.
What this page does not establish
- Whether each listed run stayed within Chandler's testing time limits (not assessed here).
- How much notice residents received for each run.
- How many generators ran on each date.
What to check next
- Compare each listed run with Chandler's notice and time rules.
- Request the generator testing logs for the scheduled dates.
- Check whether the 2026 substation work has a public permit or APS filing.