Short answer
The currently checked public record identifies this as Berry Hill campus (STACK, Project Crossroads) in Berry Hill, Pittsylvania County (Danville area), VA. Current public-status summary: Joint state and federal application filed Oct. 2026; permit decision expected by March 2027.
At a glance
- Location
- Berry Hill, Pittsylvania County (Danville area), VA
- Developer / operator
- STACK Infrastructure (end user unknown)
- Public status
- Joint state and federal application filed Oct. 2026; permit decision expected by March 2027
- Scale
- 21 buildings over 15 years; up to 3,000 MW ceiling (not guaranteed); up to 7 MGD water; $100B (WDBJ, Oct. 26, 2026)
- Map position
- City-area pin; not a parcel boundary.
What the sources establish
- The currently checked public record identifies this as Berry Hill campus (STACK, Project Crossroads) in Berry Hill, Pittsylvania County (Danville area), VA. [1] [2]
- Current public-status summary: Joint state and federal application filed Oct. 2026; permit decision expected by March 2027. [1] [2]
- Capacity / scale note: 21 buildings over 15 years; up to 3,000 MW ceiling (not guaranteed); up to 7 MGD water; $100B (WDBJ, Oct. 26, 2026). [1] [2]
What this page does not establish
- Exact building count, final load, and construction sequence unless stated in the listed documents.
- Annual water use, generator configuration, or utility agreement terms unless separately disclosed.
- Whether an approval, proposal, or court decision has changed after the sources were checked.
What to check next
- New planning-agenda, permit, zoning, and utility filings from the relevant jurisdiction.
- Air, water, and wetlands permits where applicable.
- Developer announcements that distinguish a proposal from construction or operation.